Governor of Holguín checks maintenance progress at Felton Thermoelectric Plant
- Written by Redacción ¡ahora!
- Published in Holguin
- Hits: 105
Photo: Emilio Rodríguez Pupo / Radio Mayarí
Manuel Francisco Hernández Aguilera, Governor of Holguín province, checked on the progress of maintenance work on unit one of the Lidio Ramón Pérez Thermoelectric Plant in Felton this Saturday, which ensures its synchronization with the National Electric System (SEN) with a capacity of 190 to 200 megawatts (MW).
Hernández Aguilera, accompanied by the top government and administrative officials of the municipality of Mayarí, spoke with the workers and emphasized the importance of this work for electricity generation in Cuba.
The plant's technical management reported that, on the 12th day of a 20-day schedule, the work crews are cleaning the boiler, where high levels of scale have accumulated after 14 months of continuous operation, twice the recommended six-month cycle.
Víctor Hugo González Quiala, the plant's technical director, explained that this situation forced them to extend the work by seven to ten days, as workers manually break up the hard layers of calcified residue in the confined spaces between the pipes.
The director noted that they also detected an accumulation of combustible residue causing daily internal heating in the chimney, incidents that have been systematically controlled during the 12 days since the shutdown.
Although three aggregates and the hopper remain to be cleaned, the specialists remain committed to completing the work within the planned timeframe, though they would allow one or two additional days if necessary to guarantee the machine's operational safety.
González Quiala explained to Prensa Latina that the unit's power is limited by the temperatures in the turbine bearings, a condition that prevents it from reaching its nominal potential of 245 to 260 MW. Therefore, specialized measurements will be taken, and it will be synchronized to operate at 190 to 200 MW.
The definitive solution would require a major overhaul lasting approximately 60 days, involving the complete dismantling of the machine—an unfeasible alternative under the current circumstances due to its impact on the availability of electricity, he explained.
In terms of logistics, management explained that maintaining uninterrupted 24-hour work shifts requires a weekly fuel consumption of 10,000 liters to ensure staff mobility, while the Governor of Holguín called for improved management to guarantee the necessary resources for feeding the just over 1,000 workers involved in these tasks. (Source: Prensa Latina)
