Where the light is born

hcs reparacionesfelton 01

At the Lidio Ramón Pérez Thermoelectric Power Plant, located in Felton, north of the municipality of Mayarí, in the province of Holguín, partial capitalizable maintenance work is carried out in order to return it to full operation in the shortest possible time, which guarantees a part of the electricity consumed by Cubans.

hcs reparacionesfelton 02

The group 2 turbo at this plant has been out of service for repairs since March. The actions currently being carried out are necessary to recover the generating load, reach the nominal parameters of the boiler, increase the reliability of the turbine and the generator to avoid unforeseen outages after their synchronization to the National Electroenergetic System, scheduled for the start of the summer stage.

hcs reparacionesfelton 03

Group 1 is operating, but does not generate electricity at full capacity due to dirt in the boiler that affects the optimal use of its installed power.

hcs reparacionesfelton 04

The Lidio Ramón Pérez Thermoelectric Power Plant, officially inaugurated by Army General Raúl Castro Ruz on January 5, 2001, has two thermal generation blocks that make it the plant with the largest installed generation capacity in the country, considered among the most efficient in Cuba.

hcs reparacionesfelton 05

hcs reparacionesfelton 06

hcs reparacionesfelton 07

hcs reparacionesfelton 08

hcs reparacionesfelton 09

hcs reparacionesfelton 10

hcs reparacionesfelton 11

hcs reparacionesfelton 12

 


© 2023 Periódico ¡ahora!